TKO Tunnel to Lam Tin

Project Progress

Real-time updates on the TKO Tunnel construction and development milestones

Overall Project Progress

70% Complete

The TKO Tunnel project is 70% complete and on track for opening in 2028. Major construction milestones continue to be achieved ahead of schedule. Read our latest progress report for detailed updates.

Construction Phases

Phase 1: Site Preparation

100%

Land acquisition, utility relocation, and site establishment completed.

Completed

Phase 2: Tunnel Excavation

75%

Tunnel boring operations using advanced TBM technology.

In Progress

Phase 3: Systems Installation

25%

Installation of mechanical, electrical, and safety systems.

Starting Soon

Phase 4: Testing & Commissioning

0%

System testing, safety certification, and trial operations.

Planned

Key Milestones

March 2024

Construction Commenced

Official groundbreaking ceremony and start of construction activities.

June 2024

TBM Launch

First tunnel boring machine launched from TKO portal.

September 2024

Second TBM Launch

Second tunnel boring machine launched from Lam Tin portal.

January 2025

60% Excavation Complete

Major milestone reached with 60% of tunnel excavation completed.

June 2025

Tunnel Breakthrough

Expected breakthrough when both TBMs meet at the midpoint.

December 2027

Systems Testing Complete

All tunnel systems tested and certified for operation.

Mid 2028

Tunnel Opening

Official opening of the TKO Tunnel to public traffic.

Project Statistics

2,940m
Tunnel Excavated
1,250
Concrete Segments Installed
850
Workers Employed
0
Safety Incidents